SBIR-STTR Award

Equipment and Facilities for Rapid Installation of Buried Innerduct Network for Utility Lines
Award last edited on: 7/27/2022

Sponsored Program
SBIR
Awarding Agency
DOT
Total Award Amount
$814,678
Award Phase
2
Solicitation Topic Code
-----

Principal Investigator
Lawrence M Slavin

Company Information

Outside Plant Consulting Services Inc (AKA: OPCS)

15 Lenape Avenue
Rockaway, NJ 07866
   (973) 983-0813
   lslavin@ieee.org
   www.outsideplantconsulting.com
Location: Single
Congr. District: 11
County: Morris

Phase I

Contract Number: ----------
Start Date: ----    Completed: ----
Phase I year
2004
Phase I Amount
$95,800
The feasibility of the universal placement of telecommunications and power supply lines below ground, as an alternative to their typically low-cost installation on utility poles, depends upon the availability of a cost-effective convenient method for placing and replacing cables belowground. A network of underground conduits constructed of field-assembled rigid sections, including straight segments, sweeps and bends, terminated in large manholes for access, has such characteristics but is too expensive for local distribution applications. Thus, for belowground distribution applications, cables have typically been directly buried, using either low-cost trenching of plowing methods. Unfortunately, such procedures do not offer the flexibility of future addition or replacement of cables without major disruption and/or additional significant expense. the present proposed solution comprises a coordinated, integrated system of low-cost, flexible polyethylene innerduct, readily fed off a reel, with ability to negotiate route bends as required. In contrast to other strategies being investigated in the industry, the buried innerduct network is considered to offer the best likelihood of acceptance and success. This approach is sufficiently reminiscent of present architectures to be acceptable to the utilities, yet represents an innovative solution to a difficult problem.

Phase II

Contract Number: ----------
Start Date: ----    Completed: ----
Phase II year
2007
Phase II Amount
$718,878
The proposed buried innerduct/duct network (BIN) comprises an integrated system to facilitate future upgrades of buried communications (telephony, CATV) and power lines. The objective of the project is to provide improved, cost-effective hardware and practices relative to present buried construction procedures, which do not otherwise allow for future upgrades or replacement of initially installed utility distribution lines. The BIN would therefore support and encourage present trends for placing new utilities below ground, helping avoid future problems with such installations. The shortcomings of conventional direct-buried construction methods can lead to road damage or safety problems, including risk of gas or power line hits during reconstruction activities, thereby jeopardizing continuation of the desired trends toward universal below ground facilities. The BIN may be deployed in a variety of applications, ranging from residential communities to thoroughfares and major roads. Common applications include road-widening projects (allowing replacement of existing overhead lines by new buried facilities), or any other situation in which open-trenching construction is employed. The BIN may also be installed in established areas using trenchless construction methods. The extremely successful Phase I effort, including participation and encouragement by representatives of three major utilities (SBC/AT&T, Comcast, Consumers Energy), demonstrated the feasibility of the proposed network.